Facilities Master Plan - Phase 2
Based on multiple facility studies, the District Administration and Board of Education determined that significant investment is needed to address aging infrastructure, improve efficiency, and modernize occupancy comfort. The Board recently approved a roadmap for Phase 2 of the Facility Master Plan that includes the potential for $70 million to begin these overdue improvements and ensure these facilities continue to serve our students and community well. The Board will review each individual project with a cost greater than $35,000 and approve each one on a case-by-case, needs basis. These projects represent the highest priority facility needs across our District—including, but not limited to, HVAC, fire safety, parking lots, and security systems.
The school-by-school summaries that follow provide an overview of the work planned or underway at each facility. The improvements are intended to strengthen safety, reliability, accessibility, comfort, and the long-term care of community facilities.
Questions, comments or feedback can be directed to:
Cassandra Schug, PhD
Superintendent of Schools
cschug@district100.com
Phase 2: Caledonia Elementary

Mechanical Systems
- Heating, cooling, and controls modernization: Replace aging classroom (1974 sections) and gym ventilation equipment and convert older pneumatic controls to modern digital controls. This work will provide more reliable operation and help staff manage indoor conditions more consistently.
- Fire protection improvements: Complete the building sprinkler system and evaluate the supporting water storage needs. This expands fire protection coverage throughout the school.
- Water system improvements: Replace the well pressure tank and extend hot water to classroom sinks. These updates support dependable water service and everyday use of classroom spaces. This is required by the State for health/life safety.
- Kitchen drainage improvements: Replace the kitchen grease interceptor to support proper kitchen drainage and continued food service operations.
Electrical Systems
- Security camera updates: Add interior and exterior camera coverage to identify locations to improve visibility around the school.
- Fire alarm replacement: Replace the fire alarm system so the building has updated life-safety notification and detection equipment.
- Tamper-resistant receptacles: Replace accessible electrical receptacles in student areas with tamper-resistant devices to improve safety.
- Emergency power support: Add an emergency circuit for essential kitchen refrigeration and grinder pumps to help protect critical operations during a power interruption.
Exterior Systems
- Parking, bus loop, and playground pavement: Repair and seal pavement in the parking and bus loop areas, reconstruct the southwest parking lot, and renew the hard-surface playground. The work also includes clearer pavement markings, accessibility improvements, signage, and site lighting identified.
- Building exterior maintenance: Repair masonry and building-envelope joints on the north side of the school to protect the exterior and reduce further deterioration.
- Window replacement: Replace older single-pane classroom windows and add roller shades to improve comfort, usability, and the condition of the exterior envelope.
Interior Finishes
- Ceiling replacement: Replace ceilings in the older, 1974 section of the building as part of the coordinated mechanical work.
- Door hardware updates: Replace door hardware with a standardized, interchangeable keying system to support security and efficient maintenance.
- Window shades: Add roller shades at windows that are not replaced for standardization and improved light control and classroom comfort.
Educational Adequacy
- Relocate Playground: Replace the playground farther to the east to move away from the road for improved safety. Expanding the parking lot into the existing playground’s location, to provide added parking and flexibly to reconfigure traffic circulation for safer drop-off and pick-up during these times
Phase 2: Lincoln Elementary

Mechanical Systems
- Building systems recommissioning: Review, test, and tune existing building systems and operational sequences, so they operate as intended. This process can improve reliability, comfort, and day-to-day system performance.
Electrical Systems
- Schoolwide communication system: Install an updated public address, clock, bell, and mass-notification system to strengthen everyday communication and emergency messaging.
- Security camera updates: Add exterior camera coverage at playground areas to improve visibility around the school.
Interior Finishes
- Door hardware updates: Replace door hardware with a standardized, interchangeable keying system to support security and efficient maintenance.
Phase 2: Meehan Elementary

Mechanical Systems
- Building systems recommissioning: Review, test, and tune existing building systems and operational sequences, so they operate as intended. This process can improve reliability, comfort, and day-to-day system performance.
Electrical Systems
- Schoolwide communication system: Install an updated public address, clock, bell, and mass-notification system to strengthen everyday communication and emergency messaging.
- Security camera updates: Add exterior camera coverage at playground areas to improve visibility around the school.
Interior Finishes
-
Door hardware updates: Replace door hardware with a standardized, interchangeable keying system to support security and efficient maintenance.
Phase 2: Seth Whitman Elementary

Mechanical Systems
- Building systems recommissioning: Review, test, and tune existing building systems and operational sequences, so they operate as intended. This process can improve reliability, comfort, and day-to-day system performance.
Electrical Systems
- Security camera updates: Add camera coverage at the playground and west lawn to improve visibility around the school.
- Door hardware updates: Replace door hardware with a standardized, interchangeable keying system to support security and efficient maintenance.
Phase 2: Washington Academy

Mechanical Systems
- Domestic hot water improvements: Install a new water-heating system to serve the building and kitchen and extend hot water to classroom sinks. These improvements support reliable everyday use throughout the school. This is required by the State for health/life safety.
- Art room and kitchen drainage corrections: Correct identified drain and interceptor issues in the art room and kitchen to improve drainage, prevent backups, and support continued use of these spaces.
Electrical Systems
- Lighting improvements: Complete the remaining conversion to modern light-emitting diode (LED) fixtures to improve lighting quality and system efficiency.
- Electrical service and panel replacement: Replace aging electrical service equipment and branch panels to improve reliability and support current building needs.
- Emergency power: Add an emergency generator to support essential building functions during a power interruption.
- Tamper-resistant receptacles: Replace accessible electrical receptacles in student areas with tamper-resistant devices to improve safety.
- Security camera updates: Update camera coverage in identified locations to improve visibility in and around the school.
- Fire alarm wiring: In conjunction with the HVAC upgrades, while ceilings are down, replace older fire alarm wiring so the recently updated alarm equipment is supported by a renewed system infrastructure.
Interior Finishes
- Gymnasium improvements: Refinish the gymnasium ceilings in strategic locations and drains to address interior conditions and support continued use of the space.
- Door hardware updates: Replace door hardware with a standardized, interchangeable keying system to support security and efficient maintenance.
Educational Adequacy
- Staff restroom improvement: Combine existing under-utilized, individual toilet rooms in the north wing into an updated staff restroom that better supports building needs.
Phase 2: Central Middle School

Mechanical Systems
- Digital controls modernization: Complete the conversion from older pneumatic controls to modern direct digital controls (DDC) and update controls serving major air-handling equipment. This will provide more consistent system operation, improved efficiency, and better building management.
- Mechanical room pressure correction: Address negative air pressure in the mezzanine mechanical room to support proper equipment operation and airflow.
- Building systems recommissioning: Review, test, and tune existing building systems so they operate as intended. This process can improve reliability, comfort, and day-to-day system performance.
Electrical Systems
-
Security camera updates: Add interior and exterior camera coverage to identify locations to improve visibility around the school.
Phase 2: South Middle School

Mechanical Systems
-
Digital controls upgrade: Upgrade and integrate digital controls across building systems to provide more consistent operation and better system management.
Electrical Systems
-
Lighting improvements: Update building lighting to modern light-emitting diode (LED) fixtures as part of the coordinated mechanical work. This will improve lighting quality and system efficiency.
- Security camera updates: Add interior camera coverage in the library media center and gym areas, along with exterior coverage, to improve visibility in and around the school.
- Emergency generator replacement: Replace the aging emergency generator which is currently located in the mechanical room. Relocate a new, up-sized generator set to the exterior of the building and add emergency circuits to support essential building functions during a power interruption.
- Door hardware updates: Replace door hardware with a standardized, interchangeable keying system to support security and efficient maintenance.
Educational Adequacy
-
Accessible restroom modernization: Modernize aging and high-use restroom groups near classrooms with accessible, individual-style layouts that better serve students, families, and visitors. This layout allows for improved supervision and reduced incidents in, and around, these restrooms.
-
Corridor security improvements: Add doors and security hardware to strategic corridor locations so areas of the building can be separated when needed and building access can be managed more effectively.
Phase 2: Belvidere High School

Mechanical Systems
-
Boiler plant replacement: Replace aging boilers with a modern high-efficiency boiler plant to improve heating reliability and system performance.
- Fire protection improvements: Extend the sprinkler system to areas that do not currently have coverage, using the existing ceiling system where possible.
- Air-handling and classroom ventilation replacement: Replace aging air-handling equipment and classroom unit ventilators with updated central heating, ventilation, and air-conditioning systems. This work is intended to improve reliability, ventilation, and comfort across learning spaces.
- Heating and cooling distribution modernization: Reconfigure the building water distribution system and pumping so heating and cooling can be provided simultaneously when exterior classrooms need heating and interior needs cooling during spring and fall school days. This allows for better occupant comfort throughout the school. This scope is done in conjunction with the update of HVAC equipment throughout the building.
- Chiller replacement: Replace older air-cooled chillers that use obsolete refrigerant technology while retaining the newer major chiller.
- Digital controls upgrade: Upgrade building controls so mechanical systems can be monitored and managed more consistently.
- Automotive area drainage: Replace the oil and water separator serving the automotive area to support proper drainage and continued program use.
- Kitchen drainage improvement: Increase the capacity of the drain line serving the grease interceptor to address kitchen drainage needs and prevent maintenance intensive backups.
Electrical Systems
- Electrical panel replacement: Replace identified branch electrical panels to renew aging infrastructure and improve reliability.
- Emergency power support: Add emergency circuits, with an emphasis on information technology and data spaces, so essential systems have backup power support.
- Security camera updates: Add camera coverage at identified strategic locations to improve visibility in and around the school.
- Fire alarm replacement: Replace the fire alarm system so the building has updated life-safety notification and detection equipment.
- Fire-rated door glazing: Replace older wired glass at classroom door sidelights with current fire-rated glazing.
- Door hardware updates: Replace door hardware with a standardized, interchangeable keying system to support security and efficient maintenance.
Educational Adequacy
- Restroom modernization: Modernize aging restroom groups throughout the school to improve condition, function, accessibility, and the day-to-day experience for students and visitors.
Phase 2: Belvidere North High School

Mechanical Systems
- Building systems recommissioning: Review, test, and tune existing building systems so they operate as intended. This process can improve reliability, comfort, and day-to-day system performance.
Electrical Systems
- Security camera updates: Add camera coverage in identified locations to improve visibility in and around the school.
- Emergency power support: Add emergency circuits as part of the coordinated electrical work to support essential building functions during a power interruption.
Exterior Systems
- East parking lot reconstruction: Reconstruct the east parking lot and update pavement markings, signage, and accessible parking. This work will improve pavement conditions and access to the main entrance area.
Educational Adequacy
- Athletics and physical education storage: Create an improved gym storage solution within the existing building footprint to better support athletics and physical education programs.
Phase 2: Everest High School

Electrical Systems
- Fire alarm modernization: Install a new fire alarm panel with voice notification and update alarm devices to improve life-safety communication throughout the building.
Interior Finishes
- Door hardware updates: Replace door hardware with a standardized, interchangeable keying system to support security and efficient maintenance.
Phase 2: Central Office - District Administration Building

Electrical Systems
-
Fire alarm modernization: Install a new fire alarm panel with voice evacuation and update alarm devices to improve life-safety communication throughout the building.
- Exterior security camera coverage: Add exterior security cameras where coverage is not currently available to improve visibility and safety around the building.
Exterior Systems
- West parking lot maintenance: Patch and seal the west parking lot to extend the useful life of the pavement and address areas of wear.